Upcoming events
WG Independence-Efficiency > Meetings > Bucharest 2011 > Romanian case example 3

Romanian case example 3

When notifying the result of the procedure, the Authority communicates to the tenderer that its offer is non-compliant, without specifying the reasons for non-compliance. A claim is submitted which demand the annulment of the Procedure Report which rejects the offer and notifies the result.
Is the right solution the one to accept the request for abolishing this notification, by forcing the Authority to issue a new legal notice, and to reject as early introduced the request for annulment of the Procedure Report ?