Romanian case example 3
When notifying the result of the procedure, the Authority communicates
to the tenderer that its offer is non-compliant, without specifying the
reasons for non-compliance. A claim is submitted which demand the
annulment of the Procedure Report which rejects the offer and notifies
the result.
Is
the right solution the one to accept the request for abolishing this
notification, by forcing the Authority to issue a new legal notice, and
to reject as early introduced the request for annulment of the Procedure
Report ?